default - 64 bedroom house for sale in Coney Street, York City Centre, York, YO1
Address: Coney Street, York City Centre, YorkPrice: £4,950,00010 Bedroom(s)10 Bathroom(s)Analysis Date: Oct 18, 2025
ROCE: 18.35 %Tenure Type: FREEHOLDProperty Type: HouseSize: 32101 sq ft / 2982.3 m²Risk: High RiskProject Time: 78 weeks

Investment Analysis: 48 Coney Street, York, YO1 9ND

This report analyses a unique, large-scale commercial property investment opportunity with extant planning permission for a 64-room aparthotel. While the prompt specifies a Buy-to-Let (BTL) framework, the property's nature necessitates adaptation for a commercial development context. This analysis focuses on pragmatic, profit-driven insights for a significant development project.

Rental Yield & Profitability

Annual Gross Revenue
£2,446,080
Gross Income Yield (on Purchase Price)
49.41%
Net Operating Income (NOI)
£1,519,168
Net Yield (on Purchase Price)
30.69%
ROCE (Total Capital Employed)
18.35%

The potential gross annual revenue for the 64-room aparthotel is estimated at £2,446,080, based on a conservative 75% occupancy rate and an average nightly rate of £140 per room in a prime York city centre location. After deducting estimated operational expenses of £926,912 annually, the Net Operating Income (NOI) is projected at £1,519,168. The Return on Capital Employed (ROCE) is calculated at a robust 18.35% on a total invested capital of £8,280,000 (£4.95M purchase + £3.33M development), indicating strong profitability for this development project.

Cash Flow

Monthly Gross Revenue
£203,840
Total Monthly Outgoings
£161,409
Monthly Cash Flow (Post-Mortgage)
+£42,431
Annual Cash Flow (Post-Mortgage)
+£509,168

The projected monthly cash flow after accounting for all estimated operating expenses and the assumed commercial mortgage repayment is a substantial positive £42,431. This demonstrates the significant income-generating capability of the proposed aparthotel operation, contributing to a strong annual surplus of over £500,000, assuming stable occupancy and operational performance.

Capital Growth Potential

Estimated ARV
£27,621,236
Forced Appreciation Uplift
+£19,341,236
Growth Potential Score
8/10

The primary capital growth driver is forced appreciation through the successful development of the property into a prime 64-room aparthotel and associated retail/restaurant units. The estimated After Refurbishment Value (ARV) of £27,621,236, based on a 5.5% yield on projected Net Operating Income, offers an uplift of over £19 million on the total invested capital. Combined with York's strong tourism appeal and ongoing regeneration, organic capital growth is also anticipated, making this a high-potential asset for long-term capital appreciation.

Mortgage Terms (Assumed)

Note: Mortgage details were not provided. The following are assumptions for analysis based on commercial finance for a project of this scale.

Lender Stress Test: FAIL
At a stressed rate of 8.5%, the required monthly debt service coverage increases significantly. The current projected Net Operating Income of £1,519,168 annually (£126,597 monthly) is insufficient to cover the stressed mortgage payments and maintain the required 125% coverage. This indicates a need to either secure more favourable loan terms, increase projected NOI (e.g., higher occupancy/rates, lower OpEx), or reduce the loan amount.

Upfront and Ongoing Costs

Upfront Costs

Purchase Price £4,950,000
Commercial Stamp Duty £578,250
Legal & Survey Fees £20,000
Planning & Licensing Fees £50,000
Refurbishment/Development Budget £3,330,000
Purchase Agent Fees (Est. 1%) £49,500
Total Initial Capital Invested £9,977,750

Ongoing Monthly Costs

Assumed Mortgage Payment £87,500
Management Fees (Est. 15% Revenue) £30,576
Insurance £3,333
Maintenance Fund £5,000
*(Other OpEx including Staffing, Utilities, Rates are captured in total)*
Total Monthly Outgoings £161,409

Tenant Demand

Demand for quality accommodation in prime city centre locations like York is consistently high, driven by tourism and business travel. The proposed 64-room aparthotel is strategically positioned to capture this demand.

Location Fundamentals

Location Score
9/10

Exit Strategy

The primary exit strategy is to operate the aparthotel long-term as a profitable income-generating asset. However, other viable strategies exist:

Property Condition and Potential

The property is currently retail space with Grade II listed features and requires a comprehensive redevelopment to realise its potential as a 64-room aparthotel and mixed-use scheme. The existing structure provides a substantial footprint for this ambitious project.

Refurbishment & Development Breakdown

Structural Works (incl. roof extension) £350,000
Facade Restoration (Listed Building) £200,000
M&E Installation (HVAC, Electrical, Plumbing) £850,000
Aparthotel Fit-out (64 Rooms) £1,280,000
Retail/Restaurant Unit Fit-out £300,000
Professional Fees (Architects, PM, etc.) £400,000
Contingency (approx. 10%) £400,000
Total Estimated Development Cost £3,330,000

Add Bedroom Potential: Not Applicable. The development plan is for a 64-room aparthotel. The focus is on optimising the creation and operation of these specific units and the ground-floor commercial spaces, rather than adding standard bedrooms.

Costs During Refurbishment: During the estimated 18-month development period, ongoing costs, including the assumed mortgage interest of £87,500 per month (£1,560,000 total interest), contribute significantly to the total project capitalisation. These costs must be meticulously managed and financed.

Legal and Regulatory Compliance

Risk Level & Explanation

Risk Score: 85/100

This investment carries a High Risk profile due to its scale and complexity. Key risks include significant capital expenditure, potential for construction delays and cost overruns, securing appropriate development/commercial finance, achieving projected occupancy and revenue targets for the aparthotel, and the challenges associated with developing a listed historic building. Market fluctuations in the hospitality sector also pose a risk.

Negotiation Points

Scale of Development & Capital Requirement Price Down Potential: £500,000 - £1,000,000 Confidence: 80%
Complexity of Grade II Listed Facade Restoration Price Down Potential: £150,000 - £250,000 Confidence: 85%
Risk of Planning Condition Implementation/Changes Price Down Potential: £200,000 - £400,000 Confidence: 70%
Transition from Retail to 64-Room Aparthotel Price Down Potential: £300,000 - £600,000 Confidence: 75%
Current Market Sensitivity to Hospitality Sector Price Down Potential: £200,000 - £400,000 Confidence: 60%

Refurb Shopping List

Aparthotel Room Furniture Packages (64 units) - Cost: £800,000

Ensuite Bathroom Suites & Fittings (64 units) - Cost: £500,000

Reception & Lobby Furnishings - Cost: £50,000

Communal Area Seating & Decor - Cost: £70,000

In-Room Kitchenette Appliances (Microwave, Fridge) - Cost: £30,000

Restaurant & Bar Fit-out Materials - Cost: £100,000

Retail Unit Interior Fit-out Materials - Cost: £80,000

Fire Safety Equipment & Signage - Cost: £60,000

HVAC Units & Ducting for 64 Rooms - Cost: £300,000

Plumbing & Sanitaryware Supplies - Cost: £250,000

Electrical Cabling, Sockets & Switches - Cost: £300,000

Acoustic Insulation Materials - Cost: £100,000

Internal Doors & Ironmongery (64 Rooms + common) - Cost: £120,000

Facade Restoration Materials (Stone, Render) - Cost: £150,000

Roof Extension Construction Materials - Cost: £200,000

General Building Supplies (Board, Insulation, Fixings) - Cost: £100,000

Labour Tasks

Full Property Demolition & Strip-out - Cost: £150,000

Structural Construction (New Floor, Roof Extension) - Cost: £350,000

Grade II Listed Facade Restoration & Repair - Cost: £200,000

New Mechanical & Electrical Installation (First Fix) - Cost: £850,000

Aparthotel Unit Construction & Fit-out (64 units) - Cost: £1,280,000

Bathroom Installation & Tiling (64 units) - Cost: £500,000

Retail & Restaurant Area Fit-out - Cost: £300,000

Fire Safety System Installation - Cost: £60,000

Window & Door Installation/Repair - Cost: £100,000

Flooring Installation (All Areas) - Cost: £150,000

Decoration & Finishing Works - Cost: £100,000

Project Management & Site Supervision - Cost: £200,000

MEP Second Fix & Commissioning - Cost: £150,000

Snagging, Cleaning & Handover Preparations - Cost: £100,000

Compliance Inspections & Certification - Cost: £50,000

Refurb Timeline

Total Estimated Duration: 78 Weeks || 18 Months

Phase 1: Pre-Construction (Design, Finance, Permits) || 16 weeks
Phase 2: Structural & Facade Works || 30 weeks
Phase 3: MEP Installation & Interior Framing || 24 weeks
Phase 4: Unit & Area Fit-out & Furnishing || 28 weeks
Phase 5: Testing, Snagging & Commissioning || 10 weeks

Final Investment Recommendation

Short Version

Proceed with Extreme Caution. This is a high-risk, high-reward development opportunity, not a standard BTL. The £4.95M purchase plus £3.33M development costs aim to create a £27.6M aparthotel. While returns are substantial (18.35% ROCE, £500K+ annual cash flow), the project requires significant capital, expertise, and carries substantial risks including finance, construction, and operational challenges. Due diligence on planning, costs, and finance is paramount.

Detailed Version

This analysis presents 48 Coney Street, York, as a significant commercial development opportunity with extant planning permission for a 64-room aparthotel. While framed within a BTL context, the property's scale and intended use as a serviced accommodation facility necessitate a commercial investment approach. The asking price of £4,950,000, coupled with an estimated development cost of £3,330,000, represents a total capital deployment of £8,280,000.

The projected financial performance is compelling: an estimated annual gross revenue of £2,446,080, leading to a Net Operating Income (NOI) of £1,519,168, is forecast. This yields a Return on Capital Employed (ROCE) of 18.35% and a post-mortgage annual cash flow exceeding £500,000, based on assumed commercial finance terms. Capital growth potential is substantial, with an After Refurbishment Value (ARV) estimated at £27,621,236, driven by forced appreciation through development and the asset's prime York city centre location.

However, this investment carries a high-risk profile (Score: 85/100). The primary challenges include securing £8.28M in total capital, navigating an 18-month development timeline with potential for delays and cost overruns, and successfully operating a complex aparthotel in a competitive market. The assumed commercial mortgage stress test was failed, indicating the need for careful financial structuring, potentially higher deposits or more favourable loan terms. The Grade II listed status adds a layer of complexity and cost to the restoration efforts.

Recommendation: Proceed only if the investor possesses significant experience in large-scale commercial development, hotel operations, and has access to substantial capital and development finance. Rigorous due diligence is essential, particularly concerning planning conditions, detailed costings, and securing appropriate financing that meets lender stress tests. If these hurdles can be successfully overcome, this project offers exceptional potential for profit and capital growth.